Owners and List of Contacts
Name
|
Email
|
Phone
|
Role
|
Revision History
Date
|
Reason for change(s)
|
Author(s)
|
1. Introduction
The goal and purpose of a post-mortem is to draw meaningful conclusions to help us learn from our past successes and failures by describing in detail the specific activities that were most effective and those that need adjustments prior to the next test project.
1.1 Background
1.1.1 Brief description and overview:
1.1.2 Overall approach taken to complete project:
1.1.3 The deliverables:
Planning
What Went Well?
What Did We Struggle With?
What Should We Do Differently?
Resources
What Went Well?
What Did We Struggle With?
What Should We Do Differently?
Project Management/Scheduling
What Went Well?
What Did We Struggle With?
What Should We Do Differently?
Development/Design/Specifications
What Went Well?
What Did We Struggle With?
What Should We Do Differently?
Testing
What Went Well?
What Did We Struggle With?
What Should We Do Differently?
Communication
What Went Well?
What Did We Struggle With?
What Should We Do Differently?
Team/Organization
What Went Well?
What Did We Struggle With?
What Should We Do Differently?
Product
What Went Well?
What Did We Struggle With?
What Should We Do Differently?
Management (Group and Program Managers)
What Went Well?
What Did We Struggle With?
What Should We Do Differently?
Tools and Practices
What Went Well?
What Did We Struggle With?
What Should We Do Differently?
General
What Went Well?
What Did We Struggle With?
What Should We Do Differently?
1.1.4 Anything that was special about the project:
1.1.5 Where was the most effort spent?
1.1.6 Lessons learned - things the team would/wouldn’t do again and why?
1.1.7 Where could major improvements be made to the process that was adopted?
1.1.8 Team interactions - the positives and the negatives:
1.1.9 Interactions with the customers - any difficulties?
1.1.10 In what way was the project a success/failure?
1.1.11 Was the original Root Cause Resolved?
1.1.12 Project(s) Identified but not implemented?
1.1.13 Actions Required?
1.1.14 Process Improvements Required?
2. Meaningful Conclusions:
3. Action Items:
Note: The action items themselves must be concrete and objective, that is: dates must be assigned, assignees identified, and a form of “measurement” determined so as to assess the performance towards the action item’s end objective.
Who
|
What
|
Start Date
|
End Date
|
KPI
|
No comments:
Post a Comment